Project Timeline

Implementation roadmap for the eVoucher platform

Project Gantt Chart

A 4-month implementation timeline with key milestones and deliverables.

Phase 1
Phase 2
Testing
Deployment
gantt
    title eVoucher Platform Implementation Timeline
    dateFormat  YYYY-MM-DD
    axisFormat  %b
    
    section Phase 1
    Project Kickoff           :milestone, m1, 2023-06-01, 0d
    Requirements Analysis     :a1, 2023-06-01, 14d
    Database Design           :a2, after a1, 10d
    API Development           :a3, after a2, 21d
    Admin Interface           :a4, 2023-06-20, 25d
    Basic Merchant Portal     :a5, 2023-07-01, 25d
    Basic Analytics Design    :a6, 2023-07-15, 14d
    Phase 1 Testing           :test1, 2023-07-25, 14d
    Phase 1 Deployment        :deploy1, after test1, 7d
    
    section Phase 2
    Merchant Counter App Design     :b1, 2023-08-01, 14d
    Merchant Counter App Development:b2, after b1, 21d
    Mobile App Wireframes     :b3, 2023-08-10, 10d
    Mobile App Development    :b4, after b3, 30d
    QR Code Integration       :b5, 2023-08-20, 14d
    Merchant Analytics        :b6, 2023-09-01, 14d
    Phase 2 Testing           :test2, 2023-09-15, 14d
    Final Deployment          :deploy2, after test2, 7d
    Project Completion        :milestone, m2, 2023-09-30, 0d
                                

Detailed Timeline

In-depth breakdown of tasks and deliverables for each phase.

Phase 1: Core Platform Development (Months 1-2)

Backend Development
  • Database design and architecture
  • API endpoints development
  • Authentication system
  • Voucher generation algorithm
  • QR code generation service
Admin Interface
  • Dashboard layout and design
  • Approval workflow implementation
  • Merchant management tools
  • Basic reporting functionality
  • User management system
Merchant Portal
  • Merchant registration flow
  • Basic voucher creation interface
  • Submission and approval process
  • Merchant account management
  • Basic analytics dashboard
Key Milestones
Milestone Deliverables Timeline
Project Kickoff Requirements document, project plan, team onboarding Week 1
Core API Completion Working API with documentation, authentication system Week 6
Admin Interface Launch Functional admin dashboard with approval workflow Week 7
Merchant Portal Launch Basic merchant interface for voucher creation Week 8

Phase 2: User Experience & Mobile Apps (Months 3-4)

Merchant Counter App
  • QR Code Scanner
  • Instant Validation
  • Voucher Invalidation
  • Offline Verification
  • Transaction History
User Mobile App (Ommiii)
  • Cross-platform mobile application
  • Mobile-optimized voucher display
  • QR code generation and display
  • Push notification system
  • Location-based voucher recommendations
Basic Analytics
  • Merchant dashboard metrics
  • Voucher usage tracking
  • Redemption statistics
  • Basic performance reporting
  • Export functionality
Key Milestones
Milestone Deliverables Timeline
Merchant Counter App Launch Working merchant app for voucher validation and redemption Week 12
Mobile App Beta Beta version of user and merchant mobile applications Week 14
QR Code System Completion Fully functioning QR generation and scanning system Week 15
Analytics Dashboard Basic analytics for merchants and voucher usage tracking Week 16