Implementation roadmap for the eVoucher platform
A 4-month implementation timeline with key milestones and deliverables.
gantt
title eVoucher Platform Implementation Timeline
dateFormat YYYY-MM-DD
axisFormat %b
section Phase 1
Project Kickoff :milestone, m1, 2023-06-01, 0d
Requirements Analysis :a1, 2023-06-01, 14d
Database Design :a2, after a1, 10d
API Development :a3, after a2, 21d
Admin Interface :a4, 2023-06-20, 25d
Basic Merchant Portal :a5, 2023-07-01, 25d
Basic Analytics Design :a6, 2023-07-15, 14d
Phase 1 Testing :test1, 2023-07-25, 14d
Phase 1 Deployment :deploy1, after test1, 7d
section Phase 2
Merchant Counter App Design :b1, 2023-08-01, 14d
Merchant Counter App Development:b2, after b1, 21d
Mobile App Wireframes :b3, 2023-08-10, 10d
Mobile App Development :b4, after b3, 30d
QR Code Integration :b5, 2023-08-20, 14d
Merchant Analytics :b6, 2023-09-01, 14d
Phase 2 Testing :test2, 2023-09-15, 14d
Final Deployment :deploy2, after test2, 7d
Project Completion :milestone, m2, 2023-09-30, 0d
In-depth breakdown of tasks and deliverables for each phase.
| Milestone | Deliverables | Timeline |
|---|---|---|
| Project Kickoff | Requirements document, project plan, team onboarding | Week 1 |
| Core API Completion | Working API with documentation, authentication system | Week 6 |
| Admin Interface Launch | Functional admin dashboard with approval workflow | Week 7 |
| Merchant Portal Launch | Basic merchant interface for voucher creation | Week 8 |
| Milestone | Deliverables | Timeline |
|---|---|---|
| Merchant Counter App Launch | Working merchant app for voucher validation and redemption | Week 12 |
| Mobile App Beta | Beta version of user and merchant mobile applications | Week 14 |
| QR Code System Completion | Fully functioning QR generation and scanning system | Week 15 |
| Analytics Dashboard | Basic analytics for merchants and voucher usage tracking | Week 16 |